All the mumbo-jumbo going on with SR 315 for the next two months

All the mumbo-jumbo going on with SR 315 for the next two months

614now Staff

To minimize the bobbing and weaving at the I-270/SR 315 and US 23 interchanges on the north side, roadside crews are going to have to shut down a few routes here soon.

 

Here’s what to expect according to our good friends at ODOT Columbus:

SUNDAY JUNE 25
Starting at 7 PM, SR 315 SOUTH will be reduced to one lane between Hard Road and I-270. The ramp from SR 315 south to I-270 east will be closed. This is for TWO MONTHS.
The posted signed detour is SR 315 south to I-270 west to Sawmill Rd. to I-270 east.
MONDAY JUNE 26
Starting at 7 PM, SR 315 NORTH thru traffic will be reduced to one lane between SR 161 to I-270. The ramp from I-270 east to SR 315 north will be closed. This is for TWO MONTHS.
The posted signed detour is SR 315 north to US 23 north to I-270 west to SR 315 north.
The ramp from SR 315 north to I-270 west will be closed after the evening commute until 5 AM Tuesday. The detour is SR 315 north to I-270 east to US 23 north to I-270 west.

Though timing of road closures is never perfect or convenient, the next wave of work is happening when all lanes of SR 315 are already closed south of SR 750 in Delaware County.

This work will slow down traffic so please make extra time for your commutes.